Question: a) ABC Chemicals Sdn Bhd is in progress to start their Chemical Plant Project. The list of activity and schedule of the project is proposed

a) ABC Chemicals Sdn Bhd is in progress to start

a) ABC Chemicals Sdn Bhd is in progress to start their Chemical Plant Project. The list of activity and schedule of the project is proposed as in Table below: Activity A B D E F G H 1 Duration (month) 2 3 1 3 4 3 2 5 3 Predecessor None A B B D A G E, F, H i) ii) iii) iv) Construct the network diagram, include the ES (Early start), EF (Early finish), LS (Late start) and LF (late finish) on each activity. Calculate the slack for each activity. Which path is the critical path? How long will it take to complete the project