A Activity A B C D B E F G Immediate Precessors None A A B,C...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
A Activity A B C D B E F G Immediate Precessors None A A B,C D D E,F C Normal 7 6 4 5 4 35 Crash 6 4 3 3 62 63 64 65 56 67 68 69 70 71 Assuming that indirect cost is $1,000/day. 72 73 1. The critical path and the project completion time (in normal time) are respectively 74 5 E 3 1 4 Normal Crash $7,000 $5,000 $2,000 $4,000 $3,000 $6,000 $7,000 $8,000 $6,600 $2,600 $6,400 $5,000 $7,600 $10,000 75 76 77 78 79 80 81 82 83 2. If the project needs to be shortened by four days, show activities to be crashed in the order of reduction. 84 85 86 87 3. If the project needs to be shortened by four days, what is the total cost (direct cost plus indirect cost)? 88 89 90 91 92 93 94 95 96 97 3 64 55 Problem 2 56 The project manager of a task force planning the repair of the domed stadium hopes to be able to complete 57 the construction prior to the start of the next college football season. After reviewing construction time 58 estimates, it now appears that a certain amount of crashing will be needed to ensure the project completion 59 before the season opener. The following time and cost estimates are given. 60 61 Time (in days) 62 63 64 65 66 67 75 76 77 Activity A 78 79 B C D 80 E F G Immediate Precessors None A A B,C D D E,F Normal 7 6 4 5 4 3 Crash 6 4 3 3 5 3 1 4 68 69 70 71 Assuming that indirect cost is $1,000/day. 72 73 1. The critical path and the project completion time (in normal time) are respectively 74 Direct Cost Normal $7,000 $5,000 $2,000 $4,000 $3,000 $6,000 $7,000 Crash $8,000 $6,600 $2,600 $6,400 $5,000 $7,600 $10,000 A Activity A B C D B E F G Immediate Precessors None A A B,C D D E,F C Normal 7 6 4 5 4 35 Crash 6 4 3 3 62 63 64 65 56 67 68 69 70 71 Assuming that indirect cost is $1,000/day. 72 73 1. The critical path and the project completion time (in normal time) are respectively 74 5 E 3 1 4 Normal Crash $7,000 $5,000 $2,000 $4,000 $3,000 $6,000 $7,000 $8,000 $6,600 $2,600 $6,400 $5,000 $7,600 $10,000 75 76 77 78 79 80 81 82 83 2. If the project needs to be shortened by four days, show activities to be crashed in the order of reduction. 84 85 86 87 3. If the project needs to be shortened by four days, what is the total cost (direct cost plus indirect cost)? 88 89 90 91 92 93 94 95 96 97 3 64 55 Problem 2 56 The project manager of a task force planning the repair of the domed stadium hopes to be able to complete 57 the construction prior to the start of the next college football season. After reviewing construction time 58 estimates, it now appears that a certain amount of crashing will be needed to ensure the project completion 59 before the season opener. The following time and cost estimates are given. 60 61 Time (in days) 62 63 64 65 66 67 75 76 77 Activity A 78 79 B C D 80 E F G Immediate Precessors None A A B,C D D E,F Normal 7 6 4 5 4 3 Crash 6 4 3 3 5 3 1 4 68 69 70 71 Assuming that indirect cost is $1,000/day. 72 73 1. The critical path and the project completion time (in normal time) are respectively 74 Direct Cost Normal $7,000 $5,000 $2,000 $4,000 $3,000 $6,000 $7,000 Crash $8,000 $6,600 $2,600 $6,400 $5,000 $7,600 $10,000
Expert Answer:
Related Book For
An Introduction To Statistical Methods And Data Analysis
ISBN: 9781305465527
7th Edition
Authors: R. Lyman Ott, Micheal T. Longnecker
Posted Date:
Students also viewed these general management questions
-
Della Simpson Inc. sells two popular brands of cookies, Dellas Delight and Bonnys Bourbon. Dellas Delight goes through the Mixing and Baking Departments and Bonnys Bourbon, a filled cookie, goes...
-
Assume that you recently accepted a position with Five Star National Bank & Trust as an assistant loan officer. As one of your first duties, you have been assigned the responsibility of evaluating a...
-
Assume an investor purchases 100% of an investee company for $24 million. The fair values of the identifiable net assets are as follows: Tangible net assets: Receivables, inventories, PPE, payables,...
-
A off-axis tensile test (Figure 2.14) of a unidirectional AS/3501 carbon/epoxy specimen is conducted with \(\theta=45^{\circ}\) and the applied stress is found to be \(\sigma_{x}=15.44...
-
Moe, Larry, and Curly are forming The Stooges Partnership. Moe is transferring $30,000 of personal cash and equipment worth $25,000 to the partnership. Larry owns land worth $18,000 and a small...
-
As the drawing shows, a carpenter on a space station has constructed a 30 deg ramp. A rocket moves past the space station with a relative speed of 0.884c in a direction parallel to side x. What does...
-
What is sum at the end of the following program segment? if (x>y) sum=x; else sum=y; if (z>sum) sum=z; Ox+y+z The smallest of x, y, z O The sum of x, y, z O The largest of x, y, z
-
A particle carrying a charge of \(6 \mathrm{nC}\) is at the center of a thick conducting spherical shell of inner radius \(9 \mathrm{~cm}\) and outer radius \(10 \mathrm{~cm}\). (a) What is the...
-
A flat mirror oriented perpendicular to the \(y\) axis of a Cartesian coordinate system extends along the \(x\) axis from \(x=0\) to \(x=4.0 \mathrm{~m}\). An object is located in the \(x y\) plane...
-
What is the payback period for the project described below? Machine investment MARR Annual benefit $24,999 10% $6,500 Annual maintenance $2,000 Life 10 years Salvage value $2,000
-
The light bulb in a bathroom ceiling is directly over a toy boat floating in a bathtub filled with water to a depth \(x\). How does the shadow the boat casts on the bottom of the tub compare with the...
-
A neurosurgery resident wants to double her money in the time it takes her to complete a residency program (7 years) so she can buy a new car with cash upon graduation. What interest rate is needed...
-
A corporation uses the indirect method for preparing the statement of cash flows. A fixed asset has been sold for $21,833 representing a loss of $3,539. Determine the amount that would appear in the...
-
Describe a job you have had in the past or a job you are very familiar with. Indicate the negative aspects of the job and how it could be improved with current human resource management techniques.
-
Refer to Example 8.1. In example a. Using the observed data, compute the 15 sample residuals: eij = yij yi.. b. Using the 15 residuals, verify that s2W = 1/12 Σij e2ij. c. Do the data...
-
Many people purchase sport utility vehicles (SUVs) because they think they are sturdier and hence safer than regular cars. However, preliminary data have indicated that the costs for repairs of SUVs...
-
A large used- book store randomly selected 1,000 of its customers and asked them to complete a survey about their satisfaction with the the merchandise in the store. The following data are from the...
-
The coupling is used to connect the two shafts together. Assuming that the shear stress in the bolts is uniform, determine the number of bolts necessary to make the maximum shear stress in the shaft...
-
The solid shaft has a diameter of 2 in. If it is subjected to the torques shown, determine the maximum shear stress developed in regions CD and DE of the shaft. The bearings at A and F allow free...
-
The aluminum tube has an inner diameter of 25 mm and a wall thickness of 5 mm. Determine the maximum shear stress in the fixed tube when the force of 600 N is applied to the cables. Also, sketch the...
Study smarter with the SolutionInn App