Question: a) Activity that should be crashed first to reduce the project duration by 1 day is (A) b) Activity that should be crashed next to
a) Activity that should be crashed first to reduce the project duration by 1 day is (A)
b) Activity that should be crashed next to reduce the project duration by one additional day is (B)
c) Total cost of crashing the project by 2 days = ______ $enter your response here.
Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical). Activity details are in the following table: a) Activity that should be crashed first to reduce the project duration by 1 day is b) Activity that should be crashed next to reduce the project duration by one additional day is c) Total cost of crashing the project by 2 days =$ (Enter your response as an integer.)