Question: A - An earth work project only ( 3 machines of type 1 & 2 machine of type 2 ) will be available for the

A-An earth work project only (3 machines of type 1 & 2 machine of type 2) will be available for the work find project time, Construct the project network and draw histogram Resources for two type of machine
\table[[Act.,Time/week,Resource type1,Resource type2],[1-2,4,1,2],[1-3,5,2,-],[1-4,4,1,2],[2-5,2,2,2],[3-7,1,1,-],[4-6,5,1,2],[4-7,4,1,-],[5-9,4,1,-],[6-9,3,1,1],[7-8,3,2,1],[8-9,1,3,-]]
B- What are the reasons for resource scheduling?