Question: A and D was not correct. It is also asking: How much slack does activity E have? How much slack does activity B have? How

A and D was not correct. It is also asking: How

A and D was not correct.

It is also asking:

How much slack does activity E have?

How much slack does activity B have?

How many weeks will it take to complete the project?

Suppose you want to shorten the completion time by one week, and you have the option of shortening C, D or F by one week. Which would you shorten?

Suppose you want to shorten the completion time, and you have the option of shortening B, E or F by one week. Which would you shorten?

What is the critical path?

The following activities are part of a project to be scheduled using CPM: Immediate Normal Crash Normal Activity Predecessor Time (wks)_Time (wks)_ Cost A 7 6 $7000 B 3 2 5000 4 3 9000 D B.C 5 4 3000 E 2 2000 F D 4 3 4000 EF 5 4 5000 3 4 A Crash Cost $8000 7000 9500 4500 3000 7000 8000 D 1 Suppose you want to shorten the completion time by two weeks, which two activities would you shorten? Hide answer choices a A D and G. B Cand D. CA and D. D A and C

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!