Question: a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on

a. Assuming the following information from two complex projects in the health sector have been provided to 

a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30% -69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

ANSWER Based on the tables you provided Project A has a higher risk probability and consequences compared to Project B Specifically Project A has a higher probability of failure 03 higher cost 02 and ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!