a. Assuming the following information from two complex projects in the health sector have been provided...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30% -69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30% -69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options. a. Assuming the following information from two complex projects in the health sector have been provided to aid you select a project base on project risk factor. Table la. Risk Probability and Consequences of Project A Probability of Failure Project A Maturity Complexity Dependency Project B Maturity Table Ib. Risk Probability and Consequences of Project B Probability of Failure Complexity Dependency 0.3 0.5 0.7 i. ii. iii. Cost Schedule Reliability Performance 0.1 0.3 0.3 Avoid Exploit Transfer Cost Schedule Reliability Performance Consequences 0.2 0.1 0.3 0.4 Consequences (Decision rule of thumb:70%-100%-high, 30%-69%-medium, < 30%-low) 0.2 0.6 0.3 0.8 Required: Which of the projects will you select and why? b. Under what two (2) conditions each will you adopt the following project risk response options.
Expert Answer:
Answer rating: 100% (QA)
ANSWER Based on the tables you provided Project A has a higher risk probability and consequences compared to Project B Specifically Project A has a higher probability of failure 03 higher cost 02 and ... View the full answer
Related Book For
Posted Date:
Students also viewed these general management questions
-
Managing Scope Changes Case Study Scope changes on a project can occur regardless of how well the project is planned or executed. Scope changes can be the result of something that was omitted during...
-
The following additional information is available for the Dr. Ivan and Irene Incisor family from Chapters 1-5. Ivan's grandfather died and left a portfolio of municipal bonds. In 2012, they pay Ivan...
-
Example Problem for Declining Balance Depreciation Methods Historical cost of equipment A: $120,000, purchased on January 1, 2014. Estimated salvage value: $20,000; Estimated useful life: 5 years....
-
The Excel worksheet form that appears below is to be used to recreate the Review Problem related to Harrald's Fish House. Download the workbook containing this from Connect. On the website you will...
-
The Great Pyramid of King Khufu was built of limestone in Egypt over a 20-year time period from 2580 bc to 2560 bc. Its base is a square with side length 756 ft and its height when built was 481 ft....
-
Denise Ondeyko, CPA is drafting an audit program to test controls over the Purdue Corporation's cost records. Required: 1. Explain the importance of determining the disposition of overapplied and...
-
On January 1, 2017, Loud Company enters into a 2 year contract with a customer for an unlimited talk and 5 GB data wireless plan for $ 65 per month. The contract includes a smartphone for which the...
-
In the figure an electron (e) is to be released from rest on the central axis of a uniformly charged disk of radius R. The surface charge density on the disk is +4.27 C/m. What is the magnitude of...
-
Raleigh Medical Clinic is considering acquiring 2 new ultrasound machines for $300,000. The clinic estimates that the machines will have an economic life of 4 years after which they will have zero...
-
Prove that square root 2 is an irrational number.
-
A vertical plate \(3 \mathrm{~m}\) long is at a temperature of \(400 \mathrm{~K}\) and exposed to air at \(300 \mathrm{~K}\). Calculate the thickness of the boundary layer and the value of the local...
-
Verify that the \(j\)-factor is related to the drag coefficient by the relation \[j_{\mathrm{D}}=\frac{c_{\mathrm{D}}}{2}\] for mass transfer for flow over a flat plate.
-
Integral balances can also be used for heat transfer in a turbulent-flow boundary layer if a form for the velocity profile is assumed. A common form is the 1/7th-power law:...
-
Mass transfer from a bubble. Calculate the mass transfer coefficient for the air-water system for bubbles rising at a gas velocity of \(5 \mathrm{~cm} / \mathrm{s}\) in a pool of stagnant liquid. Use...
-
A silicon substrate \(10 \mathrm{~cm}\) long is exposed to a gas stream containing an arsenic precursor so that a GaAs film can be deposited on the surface. Estimate the mass-transfer coefficient,...
-
Use the given zero to completely factor P(x) into linear factors. Zero: 3i; P(x) = x5 + 4x4 + 10x3 + 40x + 9x + 36 O (x + 4)(x - (1 - i))(x - (1 + i))(x - 3i)(x + 3i) O (x-4)(x- (1 - i))(x - (1 +...
-
If a and b are positive numbers, find the maximum value of f ( x ) = x a (9 x ) b on the interval 0 x 9.
-
Mirror Inc. is a global telecommunications company based in Canada. Its a world leader in business telecommunications and is always on the leading edge of new technology. Technology changes rapidly...
-
Complete the table below by indicating whether the transactions or economic events would increase, decrease, or have no effect on the financial ratios listed in the period they occur. Assume the...
-
Make a list of your personal assets and liabilities and try to organize them into an accounting balance sheet format. As-sign values to the assets and the liabilities. Answer the following questions...
-
Explain the significance of the microscopic and macroscopic approaches to the study of thermodynamics.
-
Why is the thermodynamic process also called cyclic process? Explain with suitable example.
-
Define isothermal, isochoric and isobaric processes with suitable examples.
Study smarter with the SolutionInn App