Question: A production process is laid out as an assembly line with four work-centers in sequence (the output of the first work-center moves to the second

A production process is laid out as an assembly line with four work-centers in sequence (the output of the first work-center moves to the second etc.). The work time needed at each center is (in minutes) 10, 12, 8, and 11 respectively. What is the maximumpossible throughput per hour of this line? (Throughputper hour = number of units made per hour; can be a fraction).

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!