Question: A production process is laid out as an assembly line with four work-centers in sequence (the output of the first work-center moves to the second
A production process is laid out as an assembly line with four work-centers in sequence (the output of the first work-center moves to the second etc.). The work time needed at each center is (in minutes) 10, 12, 8, and 11 respectively. What is the maximumpossible throughput per hour of this line? (Throughputper hour = number of units made per hour; can be a fraction).