Question: A B C D E 1 A production process at MCP Manufacturing Ltd . is shown in following Figure. The drilling operation occurs separately 2
A B
C
D
E
A production process at MCP Manufacturing Ltd is shown in following Figure. The drilling operation occurs separately
and simultaneously with, sawing and sanding, which are independent and sequential operations. A product needs to go
rough only one of the three assembly operations the operations are inparallel
Which operation is the bottleneck?
What is the bottleneck time?
What is the throughput time of the overall system?
If the firm operates hours per day, days per month, what is the monthly capacity of the manufacturing process?