Question: A B C D E F G H I J Most Optimistic 3 5 5 3 10 2 5 10 10 18 Most Likely 15

A B C D E F G H I J
Most Optimistic 3 5 5 3 10 2 5 10 10 18
Most Likely 15 8 8 10 15 5 9 15 12 20
Worst Case Time 36 24 12 15 22 8 25 33 32 30
PERT-MEAN 16.50 10.17 8.17 9.67 15.33 5.00 11.00 17.17 15.00 21.33
SD 5.50 3.17 1.17 2.00 2.00 1.00 3.33 3.83 3.67 2.00
Variance 30.25 10.03 1.36 4.00 4.00 1.00 11.11 14.69 13.44 4.00
Path Mean 129.33
SD 9.6896279

Question 1. The probability that the project will be completed in 80 days is 0.731. This is based on the PERT-MEAN of 16.50 for activity A and the standard deviation of 5.50.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Mathematics Questions!