Question: A B C D E F G H I J Most Optimistic 3 5 5 3 10 2 5 10 10 18 Most Likely 15
A B C D E F G H I J Most Optimistic 3 5 5 3 10 2 5 10 10 18 Most Likely 15 8 8 10 15 5 9 15 12 20 Worst Case Time 36 24 12 15 22 8 25 33 32 30 PERT-MEAN 16.50 10.17 8.17 9.67 15.33 5.00 11.00 17.17 15.00 21.33 SD 5.50 3.17 1.17 2.00 2.00 1.00 3.33 3.83 3.67 2.00 Variance 30.25 10.03 1.36 4.00 4.00 1.00 11.11 14.69 13.44 4.00 Path Mean 129.33 SD 9.6896279
Question 1. The probability that the project will be completed in 80 days is 0.731. This is based on the PERT-MEAN of 16.50 for activity A and the standard deviation of 5.50.