Question: A B C D Processing Time 30 mins 1.5 hours 15 mins 1 hour Under the implementation of the SPT rule, the AVERAGE FLOW TIME
| A | B | C | D | |
| Processing Time | 30 mins | 1.5 hours | 15 mins | 1 hour |
Under the implementation of the SPT rule, the AVERAGE FLOW TIME of the four jobs = _________ minutes.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts