Question: A B C Price $90 $85 $80 Raw Material $13 $14 $15 Time at Bottleneck 16 minutes 13 minutes 10 minutes Order the above projects

A B C

Price $90 $85 $80

Raw Material $13 $14 $15

Time at Bottleneck 16 minutes 13 minutes 10 minutes

Order the above projects according to the bottleneck schedule and theory of constraints?

a.

B-A-C

b.

A-B-C

c.

C-B-A

d.

A-C-B