Question: A B D E F G 9 Q2 Path ACDE is the critical path with duration 50 days; ABE's duration is 48 days. If you

A B D E F G 9 Q2 Path ACDE is the critical path

A B D E F G 9 Q2 Path ACDE is the critical path with duration 50 days; ABE's duration is 48 days. If you crash C by 3 days, ABE becomes the critical path 10 11 12 13 F Q3 Crash time is the shortest possible task duration; crash cost is the cost of completing the task in crash time 14 15 16 17 F Q4 Your customer wants you to reduce a project completion by 5 days. Only the three activities on the critical path shown below can be crashed. B NT = 7 CT = 5 NC = $10000 CC = $14000 C NT = 9 CT = 4 NC = $8000 CC = $23000 D NT = 7 CT = 5 NC = $8000 CC = $13000 18 19 20 21 22 23 24 25 a. b. Which activities would you crash? B by 2 days, C by 2 days, D by 1 day C by 5 days B by 2 days, D by 2 days c by 1 day B by 2 days, B by 3 days d. 27 28 29 30 31 32 33 34 05 expect to save $1000 in indirect costs by crashing. What would you tell your customer? a. Sure. I'll do it b. The project can't be crashed by 5 days The incentive has to b greater than $ 7,000 d. The incentive has to be greater than $10,000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!