Question: Qi Slack is defined as S = EF - ES and also as S = LF-LS T F Q2 Path ACDE is the critical path

Qi Slack is defined as S = EF - ES and also as S

Qi Slack is defined as S = EF - ES and also as S = LF-LS T F Q2 Path ACDE is the critical path with duration 50 days; ABE's duration is 48 days. If you crash Cby 3 days, ABE becomes the critical path T F Q3 Crash time is the shortest possible task duration; crash cost is the cost of completing the task in crash time T F