Question: A B F 1 2 3 4 5 6 7 D E G H Prepare a master schedule using the table displayed below. The MPS

A B F 1 2 3 4 5 6 7 D E G H Prepare a master

A B F 1 2 3 4 5 6 7 D E G H Prepare a master schedule using the table displayed below. The MPS rule is to schedule production if the projected on-hand inventory would be negative without it. Production lot size is 75 units. In addition, determine the available-to-Promise (ATP) quantity for each period. 8 3 4 1 50 2 50 35 3 50 20 50 12 5 50 60 52 9 10 11 12 13 14 15 On Hand 16 Forecast 17 Orders 18 Projected available balan 19 Available to Promise (ATP) 20 Master production Schedule 21 Lot size =75 22 23 24 25 26 20