Question: A B Seven activities are to be considered for this problem. Additional information about these activities such as their activity time and immediate predecessors are

A B Seven activities are to be considered for
A B Seven activities are to be considered for this problem. Additional information about these activities such as their activity time and immediate predecessors are included in the table that follows. Use this information to figure out the earliest completion time for this project using a Gantt chart. Activity Immediate Predecessor(s) Activity Time(in wecks) None None D 5 CD E F a. 18 wecks 1 1 4 A B E F G 5 1 4 O b. 16 weeks O c. 20 weeks O d. 14 weeks