Question: Job J is currently awaiting processing at WC202. J will require 12 hours of processing time at WC202. After WC202, J will have process requirements

Job J is currently awaiting processing at WC202.
Job J is currently awaiting processing at WC202. J will require 12 hours of processing time at WC202. After WC202, J will have process requirements of ... 6 hours at WC504 10 hours at WC603 8 hours at WC429 Standard move/queue time is calculated at 5 hours per work center. If Job J is due 88 hours from now, what is J's Slack per Remaining Operation? (Round to 2 decimal places)

Step by Step Solution