Question: a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places):

a) Based on the activity time estimates, the

a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places):

Activity

Expected Time

Variance

A

_________

_________

Part 3

B

_________

_________

Part 4

C

_________

_________

Part 5

D

_________

__________

Part 6

b) The expected completion time of the critical path = ___ weeks (round your response to two decimal places).

Part 7

The expected completion time of the path other than the critical path = ____ weeks (round your response to two decimal places).

Part 8

c) The variance of the critical path = _____weeks (round your response to two decimal places).

Part 9

The variance of the path other than the critical path = _____ weeks (round your response to two decimal places).

Part 10

d) If the time to complete the activities on the critical path is normally distributed, then the probability that the critical path will be finished in ___ weeks or less = _____ (enter as a probability and round your response to two decimal places).

Part 11

e) If the time to complete the activities on the non critical path is normally distributed, then the probability that the non critical path will be finished in

22 & 23weeks or less = (enter as a probability and round your response to two decimal places).

The estimated times and immediate predecessors for the activities in a project at Howard Umrah's retinal scanning company are given in the follow table. Assume that the activity times are independent. This exercise contains only parts a,b,c,d, and e. a) Based on the activity time estimates, the expected times and variance for each of the activities are (round your response to two decimal places)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!