Question: ( a ) Based on the information in Table 1 , draw a complete of the precedence diagram as learned in the class. [ 1

(a) Based on the information in Table 1, draw a complete of the precedence diagram as learned in the class.
[15 Marks]
(b) Given the total completion of the house is 83 weeks. Calculate the value of "y" in Table 1 AND each path's total activity time.
[7 Marks]
(c) List up THREE (3) processes exist in the knowledge area of schedule based on Project Management Body of Knowledge, 6th Edition.
[3 Marks]
Table 1: House construction
\table[[Task,Predecessors,Duration (weeks)],[A,START,12],[B,START,9],[C,A,y