Question: A _ ( blank ) _ is the approved project plan mainly consisting of scope, schedule, and cost that is not normally altered unless a

A _(blank)_ is the approved project plan mainly consisting of scope, schedule, and cost that is not normally altered unless a formal change control request is approved for modifying these plans.Question 10 Select one:a.requirement.b.baseline.c.benchmark.d.component.