Question: QUESTION 2 A is the approved project plan mainly consisting of scope, schedule, and cost that is not normally altered unless a formal change control
QUESTION
A is the approved project plan mainly consisting of scope, schedule, and cost that is not normally altered unless a formal change control request is approved for modifying these plans.
a baseline.
b component.
c requirement.
d benchmark.