Question: A bread-making factory has the production process shown in the figure below. There are five operations in sequence. The product only needs to go through

A bread-making factory has the production process shown in the figure below. There are five operations in sequence. The product only needs to go through one of the parallel machines in each case where parallel machines exist.

A bread-making factory has the production process

The process times for the work stations are given below:

Mix: 60 minutes / batch;

Proof: 70 minutes / batch;

Bake: 60 minutes / batch;

Cut: 30 minutes / batch;

Pack: 20 minutes / batch.

Assume 7 hours per day, 6 days per week, what is the weekly capacity of the process? (Round to the nearest integer).

Proof Mix Bake Pack Proof Cut Mix Bake Pack Proof

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!