Question: A bridge must be in operation by a certain date. At the data date, half of the work has been completed. BAC = US$ 1

A bridge must be in operation by a certain date. At the data date, half of the work has been completed.
BAC = US$15M
CPI =0.8
SPI =0.7
Calculate Earned Value.
US$ 15 M
US$ 10 M
US$ 7.5 M