a) Calculate the expected time and variance for each activity.
b) Use expected time of each activity from part a and determine ES, EF, LS, LF, and slack for each
activity.
c) Determine the total project completion time and the critical path for the project.
d) Compute the total project variance and project standard deviation.
e) What is the probability that the project will be finished in 48 days or less?
f) Find the probability that the project will take more than 41 days to complete.
g) What is the probability that the project due date is between 47 and 50 days?
h) What is the due date that yield a 80% chance of completion?
i) If activities H was not necessary, what impact would this have on the critical path and the number
of weeks needed to complete the project? Explain your answer.
 a) Calculate the expected time and variance for each activity. b)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!