Question: A campaign project manager has developed a program for a new awareness project in Mpumalanga. In addition, the manager has gathered the time information for
A campaign project manager has developed a program for a new awareness project in Mpumalanga. In addition, the manager has gathered the time information for each activity, as shown in the table below.
| Task | Predecessor | Duration (Days) |
|---|---|---|
| A | None | 12 |
| B | A | 4 |
| C | None | 12 |
| D | B,C | 8 |
| E | A | 7 |
| F | E | 9 |
| G | D,E | 13 |
| H | F | 5 |
| I | G | 11 |
| J | G,H | 2 |
| K | J,I | 8 |
3.1 Using the information in the table above, create an Activity on Node (AON) network diagram. 3.2 Link activity duration estimates and determine the various paths through the network in order to identify the critical path 3.3. Assuming the project starts on the 1st of March 2020. Construct a Gantt Chart for the project below.
| Task | Description | Predecessor | Duration(Days) |
| A | Order Review | None | 2 |
| B | Order Standard Part | A | 8 |
| C | Produce Standard parts | A | 5 |
| D | Design Custom Parts | A | 7 |
| E | Software development | A | 9 |
| F | Manufacture Customs Part | C,D | 8 |
| G | Assemble | B,F | 5 |
| H | Test | E,G | 5 |