Question: A campaign project manager has developed a program for a new awareness project in Mpumalanga. In addition, the manager has gathered the time information for

A campaign project manager has developed a program for a new awareness project in Mpumalanga. In addition, the manager has gathered the time information for each activity, as shown in the table below.

Task Predecessor Duration (Days)
A None 12
B A 4
C None 12
D B,C 8
E A 7
F E 9
G D,E 13
H F 5
I G 11
J G,H 2
K J,I 8

3.1 Using the information in the table above, create an Activity on Node (AON) network diagram. 3.2 Link activity duration estimates and determine the various paths through the network in order to identify the critical path 3.3. Assuming the project starts on the 1st of March 2020. Construct a Gantt Chart for the project below.

Task Description Predecessor Duration(Days)
A Order Review None 2
B Order Standard Part A 8
C Produce Standard parts A 5
D Design Custom Parts A 7
E Software development A 9
F Manufacture Customs Part C,D 8
G Assemble B,F 5
H Test E,G 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!