Question: A Construction project manager has developed a program for a new construction campaign. In addition, the manager has gathered the time information for each activity,
A Construction project manager has developed a program for a new construction campaign. In addition, the manager has gathered the time information for each activity, as shown in the table below.
- Calculate the expected activity times (round to nearest integer). (10 Points, LO4)
- Identify the critical path. What are the alternative paths and how much slack time is associated with each non-critical path? (15 Points, LO2)
- Calculate the activity slacks. What is the total project length? Make sure you fully label all nodes in the network. (5 Points, LO5)
- Identify the burst activities and the merge activities. (5 Points, LO3)
- Given the activity variances, what is the likelihood of the project finishing on week 36? (10 Points, LO4)
- Suppose you wanted to have a 99% confidence in the project finishing on time. How many additional weeks would your project team need to negotiate for in order to gain this 95% likelihood? (5 Points, LO4)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts