Question: (A) Carl's team should be able to complete the project in ____ days. (B)The longest path will be ____. In the following table the activities

(A) Carl's team should be able to complete the project in ____ days.
(B)The longest path will be ____.
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity Immediate Predecessor(s) Time (days) A 5 A 4 6 6 D E F B B 4 4 D E, F 6 8Step by Step Solution