Question: Homework: Assignment 3: Project Management Question 1, Problem 3.5b Part 1 of 2 HW Score: 5.56%, 0.33 of 6 points O Points: 0 of
Homework: Assignment 3: Project Management Question 1, Problem 3.5b Part 1 of 2 HW Score: 5.56%, 0.33 of 6 points O Points: 0 of 1 in the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working Activity Immediate Predecessor(s) Time (days) Carf's team should be able to complete the project in days B C D E 4 C 4 G D E. F 7