Question: A certain company is planning to run a project whose activities are summarized in the table below. Task ID Description Immediate Predecessor Duration ( months
A certain company is planning to run a project whose activities are summarized in the table below.
Task ID
Description
Immediate Predecessor
Duration months
Install New Software Package
Assess Requirements
Assess Requirements
Design
Design Business System
Develop
Modify Purchased Package
ModifyInHouse Procedures
Modify Manual Systems Flow
Test
Test Purchased Package
Test InHouse Procedures
Test Manual Systems Flow
Implement
Implement New Software Package
Train Staff
a How many months will it take to complete the project?
b Which activities are critical?
c What is the total slack for each of the activities that are not critical?
d If the project were started on June and observed all the US Legal holidays, on what day will the project be completed?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock