Question: Use the following data to construct a network diagram and answer the questions below (NB: You may use ProjectLibre or MS Project or do it
Use the following data to construct a network diagram and answer the questions below (NB: You may use ProjectLibre or MS Project or do it in MS Word or by hand)
| Task ID | Description | Immediate Predecessor | Duration (Weeks) |
| A | Assess business requirements | -- | 4 |
| B | Design system | A | 10 |
| C | Purchase software apps | B | 8 |
| D | Modify in-house procedures | B | 6 |
| E | Modify systems flow | B | 16 |
| F | Install and test purchased apps | C | 6 |
| G | Test in-house procedures | D | 4 |
| H | Test systems flow | E | 4 |
| I | Implement new software apps | F,G,H | 6 |
| J | Train staff | F,G,H | 2 |
Which activities are on the critical path?
How long will it take to complete the project?
If it became imperative that you reduce the project duration by two weeks, which activities would you consider expediting? Why?
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts