Question: A certain part (0438) requires three assembly operations (L, M and Q) that are sequentially done on an automatic assembly line. The schedule designer requires
A certain part (0438) requires three assembly operations (L, M and Q) that are sequentially
done on an automatic assembly line. The schedule designer requires this assembly line to
produce 6000 parts/month, and the plant will be operating 4 weeks per month, six days per
week, and 8 hours per day. The following information is known:

The line is controlled by a computer that requires re-programing every lot of 750 parts.
This re-programing process takes 1 hour on average.
a) The required input to the automatic assembly line is:
b) The available time in (hours) at operation (M) for producing the required quantity is:
c) The required time in (hours) for operation (Q) to produce the required quantity is:
d) The fraction of the control computer programming process is:
e) The number of automatic assembly lines required to produce the 6000 units/months
is:
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock