Question: A change control system is ? a . The processes required to ensure that the project is completed within the approved budget b . Devising

A change control system is?
a. The processes required to ensure that the project is completed within the approved budget
b. Devising and maintaining a workable scheme to ensure that the project addresses the organization's needs
c. A management review that should occur after each project phase to determine if projects should be continued, redirected, or terminated; also called a kill point
d. A formal, documented process that describes when and how official project documents may be modified, the people authorized to make modifications, and the paperwork required for these changes.
 A change control system is? a. The processes required to ensure

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!