Question: A change request in a project was rejected some weeks ago. Yesterday, the project manager found out that it was nevertheless implemented by team members,
A change request in a project was rejected some weeks ago. Yesterday, the project manager found out that it was nevertheless implemented by team members, who received information about the request but missed the communication on the rejection. In order to avoid such a situation, what could have improved communications and avoided the misunderstanding? Question 39 options: Changing the communication method Changing the communication style Asking for an acknowledging message. Nothing different