Question: A change request in a project has been rejected some weeks ago. Yesterday, the project manager found out that it nevertheless has been implemented by
A change request in a project has been rejected some weeks ago. Yesterday, the project manager found out that it nevertheless has been implemented by the team members, who knew of the change request, but not of the rejection. In order to avoid such a situation, rejected change requests should be consistently communicated to stakeholders through which process