Question: A chart that captures, by resource, the specific amount of time that the particular resource is scheduled to be worked over a predetermined time period

A chart that captures, by resource, the specific amount of time that the particular resource is scheduled to be worked over a predetermined time period is known as a: Question 17Select one: a. Gantt chart b. Risk responsibility chart c. Resource histogram d. Responsibility assignment matrix