Question: a . Choose the correct project network diagram below. A . A B C D E F G x y graph B . A B

a. Choose the correct project network diagram below.
A.
A
B
C
D
E
F
G
x y graph
B.
A
B
C
D
E
F
G
x y graph
C.
A
B
C
D
E
F
G
x y graph
D.
A
B
C
D
E
F
G
x y graph
Part 3
b. Identify all the paths through the network and their lengths. Fill in the table below (enter your responses rounded to one decimal place).
Part 4Part 5Part 6Part 7
Path
Length(days)
A-C-
G
E
E-G
F
F-G
enter your response here
A-
F
D
B-D
B-C
B
-E-G
enter your response here
A-
D-F
C-D
F
B-D-F
B-C-D
-G
enter your response here
B-A
B-D
A-B
D
B
-E-G
enter your response here
B-
E
F
C-D
D-F
-G
enter your response here
Part 8
c. The critical activities are
B, D, F, and G
A, C, E, and G
B, D, E, and G
A, D, F, and G
A, D, E, and G
so they make up the critical path.
Part 9
The entire project will take
enter your response here days to complete. (Enter your response rounded to one decimal place.)
Part 10
d. Management would like to complete the project in less than 19 days. Management has determined that activity Upper E can be crashed 6days, for a total cost of $7 comma 500. No other activities can be crashed.
After crashing,
B, D, E, and G
A, D, E, and G
B, D, F, and G
A, D, F, and G
A, C, E, and G
is the critical path. The entire project will take
enter your response here days. (Enter your response rounded to one decimal place.)
Part 11
Crashing activity Upper E
will not
will
meet management's goal of less than 19 days.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!