Question: Consider the following project activities. LOADING... Click the icon to view the project activities. Part 2 a . Choose the correct project network diagram below.

Consider the following project activities.
LOADING... Click the icon to view the project activities.
Part 2
a. Choose the correct project network diagram below.
A.
A
B
C
D
E
F
G
x y graph
B.
A
B
C
D
E
F
G
x y graph
Your answer is correct.C.
A
B
C
D
E
F
G
x y graph
D.
A
B
C
D
E
F
G
x y graph
Part 3
b. Identify all the paths through the network and their lengths. Fill in the table below (enter your responses rounded to one decimal place).
Part 4Part 5Part 6Part 7
Path
Length(days)
A-C-
E-G
18
A-
D
-E-G
23.5
A-
D-F
-G
19.5
B-D
-E-G
25.5
B-
D-F
-G
21.5
Part 8
c. The critical activities are
B, D, E, and G
so they make up the critical path.
Part 9
The entire project will take
25.5 days to complete. (Enter your response rounded to one decimal place.)
Part 10
d. Management would like to complete the project in less than 23 days. Management has determined that activity Upper E can be crashed 4.5days, for a total cost of $7 comma 500. No other activities can be crashed.
After crashing,
B, D, E, and G
is the critical path. The entire project will take
21 days. (Enter your response rounded to one decimal place.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!