Question: A client has called you to let you know that they need to move up the deadline to have the product your project is creating
A client has called you to let you know that they need to move up the deadline to have the product your project is creating for a tradeshow. They'd like you to do whatever you can without adding costs to the project schedule. Which one of the following is the best choice for this scenario?This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A Fast tracking the project activities option B Crashing the project option C Adding lag time to non-critical path activities option D Changing the critical path