Question: A Cloud migration project is scheduled to last 2 0 months with a budget of $ 1 , 8 0 0 , 0 0 0

A Cloud migration project is scheduled to last 20 months with a budget of $1,800,000. At the end of
month 5, the project is 25% complete. Calculate CPI, SPI, EAC, and ETC?
Also, explain the interpretation of these matrices.