Question: A company contracts a software vendor to implement and customize a new software application and assigns a project manager to initiate and lead the project.
A company contracts a software vendor to implement and customize a new software application and assigns a project manager to initiate and lead the project. Which of the following inputs to the project charter describes the key deliverables?
ABusiness case
BAgreements
CProject scope statement
DProject schedule