Question: A company has completed building a new datacenter. The project has many changes that were submitted to the change control board. Most changes were approved,

A company has completed building a new datacenter. The project has many changes that were submitted to the change control board. Most changes were approved, and some were not. Which of the following is not a purpose of the change control board?a. Deny changes whenever possible b. Manage the change control processc. Assess changed. Stop unnecessary changes