Question: A company has developed a project using CPM but is interested in accelerating it if possible. The project has the following activities, duration (in weeks),

A company has developed a project using CPM but is interested in accelerating it if possible. The project has the following activities, duration (in weeks), costs, and precedence relationships:

Activity

Immediate

Predecessor

Normal

Time

Crash

Time

Cost per week

To Crash

A

----

5

3

$ 60

B

A

5

2

$ 30

C

A

4

---

----

D

A

2

1

$ 40

E

B,C,D

3

1

$ 50

What is the project completion time of the entirely crashed project and total crashing cost?