Question: A company has developed a project using CPM but is interested in accelerating it if possible. The project has the following activities, duration (in weeks),
A company has developed a project using CPM but is interested in accelerating it if possible. The project has the following activities, duration (in weeks), costs, and precedence relationships:
| Activity | Immediate Predecessor | Normal Time | Crash Time | Cost per week To Crash |
| A | ---- | 5 | 3 | $ 60 |
| B | A | 5 | 2 | $ 30 |
| C | A | 4 | --- | ---- |
| D | A | 2 | 1 | $ 40 |
| E | B,C,D | 3 | 1 | $ 50 |
What is the project completion time of the entirely crashed project and total crashing cost?