Question: A company has two activity cost pools: machine setups and production orders. The total cost in the machine setup activity cost pool is $200,000 and
A company has two activity cost pools: machine setups and production orders. The total cost in the machine setup activity cost pool is $200,000 and the total cost in the production orders cost pool is $80,000. The estimated activity is 20,000 setups and 5,000 production orders. What is the activity rate for the machine setup activity cost pool