Question: A company is doing a software installation project. Here is the initial resource load chart for the project: At day # 5 there will be

A company is doing a software installation project. Here is the initial resource load chart for the project: At day \# 5 there will be a resource conflict. They need eight software testers that day but they only have five. Which activit(ies) should be committed to the schedule that day? Activities \#5 (load testing) and \#6 (use case testing) Activity \#5 (load testing) only Activities \#5 (load testing) and \#4 (compatibility testing)