Question: A company is managing two different projects: a small project with low risk and a large project with high risk. Why is tailoring necessary for
A company is managing two different projects: a small project with low risk and a large project with high risk. Why is tailoring necessary for both projects?
To ensure that both projects have the same level of planning and control
To ensure that the project management approach is appropriate for the unique characteristics of each project
To reduce the time and cost required for project management
To minimize the involvement of stakeholders in project management