A company of engines works 6 days a week with 2 shifts a day. Every shift is
Fantastic news! We've Found the answer you've been seeking!
Question:
A company of engines works 6 days a week with 2 shifts a day. Every shift is of 680 minutes. The break for lunch is 35 minutes. In the period of 15 weeks, the customer's request is 4768 engines. Calculate the takt time in the period. The takt time should be in seconds and you should round it up to the nearest whole number.