Question: A company uses EVM for its projects. Activity A is supposed to be 90 percent complete with a budgeted cost to complete of $130; itis
A company uses EVM for its projects. Activity A is supposed to be 90 percent complete with a budgeted cost to complete of $130; itis 80 percent complete in actuality.Activity Bis supposed to be 85 percent complete with a budgeted cost to complete of $75; itis 70 percent complete in actuality.Activity Cis supposed to be 10 percent complete with a budgeted cost to complete of $1200; itis 15 percent complete in actuality.Activity Dis supposed to be 30 percent complete with a budgeted cost to complete of $100; itis 35 percent complete in actuality.Activity Eis supposed to be 15 percent complete with a budgeted cost to complete of $110; itis 10 percent complete in actuality. The total actual cost incurred so far is $1135.
a. What is the cost performance index? Round your final answer to two decimal places.
b. What is the schedule performance index? Round your final answer to two decimal places.
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
