Question: A company uses EVM for its projects. Activity A is supposed to be 9 0 percent complete with a budgeted cost to complete of $

A company uses EVM for its projects. Activity A is supposed to be 90 percent complete with a budgeted cost to complete of $130; it is 80 percent complete in actuality. Activity B is supposed to be 85 percent complete with a budgeted cost to complete of $75; it is 70 percent complete in actuality. Activity C is supposed to be 10 percent complete with a budgeted cost to complete of $1200; it is 15 percent complete in actuality. Activity D is supposed to be 30 percent complete with a budgeted cost to complete of $100; it is 35 percent complete in actuality. Activity E is supposed to be 15 percent complete with a budgeted cost to complete of $110; it is 10 percent complete in actuality. The total actual cost incurred so far is $1135.
What is the schedule performance index? Round your final answer to two decimal places.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!