Question: A companys planned activity level for next year is expected to be 100000 machine hours. At this level of activity, the company budgeted the following
A companys planned activity level for next year is expected to be 100000 machine hours. At this level of activity, the company budgeted the following manufacturing overhead costs:
| Variable | Fixed | |||
| Indirect materials | $200000 | Depreciation | $60000 | |
| Indirect labor | 240000 | Taxes | 10000 | |
| Factory supplies | 24000 | Supervision | 50000 | |
A flexible budget prepared at the 80000 machine hours level of activity would show total manufacturing overhead costs of
|
| $371200. |
|
| $491200. |
|
| $464000. |
|
| $467200. |