Question: A complex project network diagram includes +100 activities. The ending activities of the network diagram are A1, A2, to A9 with the Early Finish of

A complex project network diagram includes +100 activities. The ending activities of the network diagram are A1, A2, to A9 with the Early Finish of A1 as the largest and the Early Finish of A9 as the smallest Early Finishes. Which statement is correct? Select one:

The Late Finish of each ending activity is equal to the Early Finish of the same ending activity

The Late Finish of all ending activities is equal to the Late Finish of A9

The Late Finish of all ending activities is equal to the Late Finish of A1

The Late Finish of each ending activity is equal to the average of the Early Finishes of all ending activities.

None of the given answers is correct, numerical values are needed.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!