Question: A complex project network diagram includes +100 activities. The ending activities of the network diagram are A1, A2, to A9 with the Early Finish of
A complex project network diagram includes +100 activities. The ending activities of the network diagram are A1, A2, to A9 with the Early Finish of A1 as the largest and the Early Finish of A9 as the smallest Early Finishes. Which statement is correct? Select one:
The Late Finish of each ending activity is equal to the Early Finish of the same ending activity
The Late Finish of all ending activities is equal to the Late Finish of A9
The Late Finish of all ending activities is equal to the Late Finish of A1
The Late Finish of each ending activity is equal to the average of the Early Finishes of all ending activities.
None of the given answers is correct, numerical values are needed.