Question: a comprehensive rebaselining effort responding to problems by adjusting the remaining work from the contractors original plan such that it is completed within the remaining
a comprehensive rebaselining effort responding to problems by adjusting the remaining work from the contractors original plan such that it is completed within the remaining budget and schedule is best described as internal replanning